The brief
The owner needed 24 bungalows on a pine-covered slope, keeping the natural gradient and opening before peak season.
Our solution
Light-gauge steel frames on small pile foundations, with no levelling. Components shipped in 4 batches of 6 units, with crews working in parallel.
Result
Completed in 9 weeks, every batch on schedule. The resort opened as planned.